Main content

Road Construction

Iroquois Avenue Waterline & Roadway Replacement Project

Iroquois Avenue Waterline & Roadway Replacement Project is tentatively scheduled to start on 07/21/2025. SD Ireland Brothers Corporation will be replacing the existing waterline along Iroquois Avenue from South Summit Street to the Orchard Terrace intersection. In addition, the project includes the full reconstruction of the roadway from South Summit Street to Orchard Terrace, as well as the repaving of the roadway from Orchard Terrace to Park Street.

Throughout construction, we will be sending out daily emails about the progress and anticipated schedule as they may relate to access and disruptions to the adjacent properties. An initial email will be sent during the week of July 14th as a reminder of the July 21st start date.

To receive daily project email updates that will include information about the project status and project scheduling, please send an email requesting to be added to the project email distribution list to the following email address: IroquoisAve@ dlhce.com.

Daily Project Update: 11/26/2025

Today the Contractor adjusted storm and sewer structures along Iroquois Avenue between Orchard Terrace and Park Street.

Today was the last day of construction work on this project for this year. Next week there will be a final site walkthrough, and there may be some minor clean-up work following the walkthrough. The Contractor will be back in the spring to ensure there is grass growth and to finish any remaining clean-up work on the areas disturbed by the construction.

Iroquois Avenue is now open to all traffic.

This will be the last daily email sent for this project until spring. As mentioned above, there may be some minor clean-up work in the next week or so, but we do not anticipate significant impacts to properties or traffic.

A big THANK YOU to all of you for your patience and cooperation throughout this project.


Construction Update Williston VT 2A and Industrial Ave Project

DATE: Friday, November 14, 2025

TRAFFIC IMPACT AND DURATION:From Monday, November 17, to Friday, November 21, between 6:30 a.m. and 5 p.m., Vermont Route 2A (VT 2A) between Meadowrun Road and River Cove Road may have lane reductions and lane shifts. Drivers should slow down and use caution when traveling through the project area. Drivers are encouraged to plan for extra travel time or use alternate routes.

CONSTRUCTION ACTIVITIES: Next week, crews will continue applying line striping and pavement markings throughout the project area, including at the VT 2A and Industrial Avenue intersection. All line striping activities are weather-dependent.

The contractor will also continue preparing the project area for winter shutdown by completing general cleanup and removing construction equipment and materials.

PROJECTED COMPLETION: Fall 2026

PROJECT FACTSHEET                       

SIGN UP FOR EMAIL PROJECT UPDATES

CONTACT:

Elaine Ezerins
Public Information Consultant
(603) 782-2460
elaine.ezerins@ wsp.com